TJ Priok Power Station

Location

Jakarta, Indonesia

Period

Phase 1: Nov-Dec 2017
Phase 2: June-July 2018

Category

Power Station Installation

Project Gallery

Project Photo 1
Project Photo 2
Project Photo 3
Project Photo 4
Project Photo 5
Project Photo 6
Project Photo 7
Project Photo 8
Project Photo 9
Project Photo 10
Project Photo 11
Project Photo 12
Project Photo 13

Phase 1 Cargo (Nov - Dec 2017)

2 Units GT (Gas Turbine)

Weight: 420 Tons

2 Units GTG (Gas Turbine Generator)

Weight: 308 Tons

Phase 2 Cargo (June - July 2018)

1 Unit ST (Steam Turbine)

Weight: 145 Tons

1 Unit STG (Steam Turbine Generator)

Weight: 308 Tons

Equipment Supplied

  • • SBL 1100 (4 Point lift system)
  • • Tower Structure

Interested in Similar Projects?